2010 AA Solvency II

Solvency II: Implementation Challenges & Experiences Learned Appointed Actuary Symposium Actuarial Society of Hong Kong...

0 downloads 228 Views 893KB Size
Solvency II: Implementation Challenges & Experiences Learned

Appointed Actuary Symposium Actuarial Society of Hong Kong (ASHK) Jonathan Zhao - Actuarial Services Practice Leader, Asia Pacific 3 November 2010

Agenda



Solvency II introduction & recap



Implementation procedures



Experiences & lessons from QIS 5



Looking ahead

Page 2

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Solvency II introduction & recap



Solvency II introduction & recap



Implementation procedures



Experiences & lessons from QIS 5



Looking ahead

Page 3

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Solvency II introduction & recap Background ►

Solvency II is the proposed new Europe-wide framework for prudential supervision of insurance



Aims to address problems with Solvency I - Outdated system - Insufficiently risk-sensitive - Does not reflect best practice - Difficulties in supervising multinational, diversified groups



A fundamental change to Solvency requirements: - Principles based approach to supervision - Market consistent approach for valuing liabilities - Capital requirements linked to risk profile - Convergence of economic capital and regulatory capital - Major focus on risk management - Significant disclosure requirements - Capital add-ons for deficiencies - Links to other reporting measures

Page 4

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Solvency II introduction & recap We are here

Regulatory timeline and implementation activities

2009 May 2009 – Framework Directive Approved

European

CEIOPS/ > EIOPA >

Regulatory timetable

QIS5 feedback

2012 October 2011 – Level 2 Directive Approved

Internal Model Application Process (IMAP) submission

Legislative process

Impact study of L2 (Commission)

Planning for implementation in 30 countries and associated territories

Interactive – firms & FSA

Vision & Gap analysis

Road Map design

Implementation – 31 December 2012

Develop guidance under Level 3

L2 drafting (Commission and EIOPC)

UK

Implementation activity

QIS5

Level 2 advice to Commission

Member States

Page 5

2011

2010

IMAP dry run (June 2010 to October 2011)

Transposition into domestic law and regulation IMAP by April 2012

Full implementation

Build and test Detailed Implementation design

Embed Implementation

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Solvency II introduction & recap Frame work – 3 Pillar Approach

Risk Quantifications

Risk Management

Risk Transparency

Pillar 1

Pillar 2

Pillar 3

Quantitative Capital Requirements

Supervisory activities

Supervisory reporting & public disclosure

Risk Governance

Transparency & Disclosure

Solvency Capital Requirements (SCR) Minimum Capital Requirements (MCR)

A risk oriented framework

Page 6

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Pillar 1

Pillar 1

Pillar 2

Pillar 3

Technical Provisions

Risk Management

MCR Minimum Capital Requirement

Own Risk and Solvency Assessment (ORSA)

DisclosureSolvency & Financial Condition Report

SCR Solvency Capital Requirement

Supervisory powers & processes

Market Discipline

Model Approval

Page 7

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Solvency II – Pillar 1 Market consistent balance sheet The starting point for Solvency II is an economic, market-consistent approach to the valuation of assets and liabilities. Alignment as far as possible between Solvency II and IFRS 4 Phase II. Solvency II Balance Sheet

Free Surplus



Assets are valued at market value



Technical provisions = BEL + Risk Margin Best Estimate Liability (BEL) ► Best estimate of all future cash flows discounted at a risk free rate with adjustment for illiquidity premium ► Risk free rate is derived from swap rates less an adjustment for credit risk (10bps), level of illiquidity premium various by contract type (50bps – 100bps) + Risk Margin ► Cost of capital method will 6% factor used for QIS 5, IFRS 4 Phase II suggested 3 methods (CI, CTE and CoC)

Own Funds SCR

MCR

Assets

Risk margin

Technical provisions

Best estimate liability



Capital requirements ► ► ►

Page 8

SCR = first regulatory intervention point (VaR @99.5% CI over 1 year) – Standard Formula or Internal Model MCR = final regulatory intervention point (VaR @85% CI over 1 year) Framework directive has also set MCR to a minimum of 25% and a maximum of 45% of the SCR

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Solvency II – Pillar I Structure of standard formula for SCR SCR = BSCR + Adj + Op Risk Adj

Market

Def ault

Health

Interest rate

SLT Health

Equity

BSCR

Health CAT

Operational Risk

Lif e

Non-Lif e



SCR intangibles risk module introduced for QIS 5.



SCR illiquidity premium sub-module introduced for QIS 5.



Health risk module split between SLT (similar to life techniques) and NonSLT – some reduction in QIS5 for certain correlations between sub-module risks. Health CAT risk introduced (as per Final Advice although the CAT risk is now aggregated across SLT and NonSLT).



A lapse risk module for Non Life business has been introduced to recognise the impact if policy take-up rates were lower than expected.

Intangibles

Non-SLT Health

Mortality

Premium Reserve

Mortality

Premium Reserve

Longevity

Lapse

Property

Longevity

Lapse

Disability Morbidity

CAT

Spread

Disability Morbidity

Currency

Lapse

Concentration

Expenses

Revision

Illiquidity

Revision

CAT

Lapse

Basic SCR correlations

Expenses

Market

Life

Health

Market

1

Default

0.25

1

Life

0.25

0.25

1

Health

0.25

0.25

0.25

1

Non-Life

0.25

0.5

0

0

= included in the adjustment f or the risk mitigating ef f ect of future prof it sharing

Page 9

Default

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Non-Life

1

Solvency II - Pillar 2

Pillar 1

Pillar 2

Pillar 3

Technical Provisions

Risk Management

MCR Minimum Capital Requirement

Own Risk and Solvency Assessment (ORSA)

DisclosureSolvency & Financial Condition Report

SCR Solvency Capital Requirement

Supervisory powers & processes

Market Discipline

Model Approval

Page 10

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Pillar 2 Requirements ►





The key requirement of Pillar 2 is for firms to have a system of governance to “provide for sound and prudent management of the business”. This system of governance “shall at least include an adequate transparent organisational structure with a clear allocation and appropriate segregation of responsibilities and an effective system for ensuring the transmission of information”. Supporting this requirement are six key “aspects” based on conditions and functions which the Directive expects Firms to address and have in place:

Conditions ► Fitness and Propriety ► Outsourcing ► Internal Control Functions ► Risk Management Function ► Internal Audit Function ► Actuarial Function Pillar 2 can be split in two – Governance and ORSA

Page 11

Evidencing Successful Pillar 2 Implementation Governance ► Clear and documented delegation of authority cascading through the organisation with appropriate spans of control and suitable persons holding roles ► Suitable allocation of function responsibility that avoids duplication ► Clear articulation of committee responsibilities split between “doing” and “oversight” and “assurance”. ► Policies that set out how the business is overseen and controlled and that reflect the current reality ► Risk information to support individuals and committees in their roles across the lines of defence Own Risk and Solvency Assessment (ORSA) ► A demonstrable strategy and appetite for risk that is cascaded down through the organisation ► A process for identifying all the risks to the business, quantifying them across a range of outcomes controlling them and reporting within them within the governance arrangements set out ► A dynamic approach to using risk information within the business on a timely basis

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Pillar 2 Own Risk and Solvency Assessment The ORSA is the regular practice of assessing overall capital needs with a view to the firm’s specific risk profile that forms part of the risk management system. It is: ► an internal assessment process and as such should be embedded in strategic decisions, and ► a supervisory tool for the supervisory authorities.

“3 lines of defence” model – a possible approach to meet Solvency II requirements Board Strategy, risk appetite and policy

The ORSA can be defined as the entirety of the processes and procedures employed to identify, assess, monitor, manage, and report the short and long term risks that the business faces or may face and to determine the own funds necessary to ensure that its overall solvency needs are met at all times. The ORSA aims at enhancing awareness of the interrelationships between the risks the business is currently exposed to, or may face in the long term, and the internal capital needs that follow from this risk exposure. The ORSA needs to be supported by an effective and robust escalation process paying particular attention to

Functional escalation ► Risk exposures and the linkages to decision making ►

Page 12

1st

Line

Risk Ownership

2nd Line

3rd Line

Risk Control and Monitoring

Independent Assurance

Executive Committee

Oversight Committee

Audit Committee

Supported by Risk Taking Business Units

Supported by Compliance, Actuarial, Risk Management and Risk Modelling Functions

Supported by Internal Audit

Risk Management Systems Own Risk and Solvency Assessment Internal Control Framework

The ORSA process for assessing and monitoring overall solvency builds on the Pillar I SCR calculation by articulating the firm’s view of required capital. It should form an integral part of the business planning of the organisation. A key challenge will be integrating the appropriate modelling approaches into the risk framework and ORSA.

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Solvency II - Pillar 3

Pillar 1

Pillar 2

Pillar 3

Technical Provisions

Risk Management

MCR Minimum Capital Requirement

Own Risk and Solvency Assessment (ORSA)

Disclosure - Solvency & Financial Condition Report

SCR Solvency Capital Requirement

Supervisory powers & processes

Market Discipline

Model Approval

Page 13

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Pillar 3 Overview Three aspects: Report to Supervisor – RTS Information to submit to regulator ► ► ►





Solvency and Financial condition report - SFCR Public disclosures – at least annually

Disclosures by regulators

RTS and SFCR will contain a qualitative report, including quantitative data and quantitative reporting templates Proportionality principle: detail of information is in line with nature, scale and complexity of risks inherent in the business Need a written disclosure policy approved by the management body to ensure appropriate governance procedures and practices so that information is complete, consistent and accurate (on an ongoing basis) There are provisions to avoid competitors of the undertaking gaining significant undue advantage – non-disclosure of information in specific cases need to be explicitly mentioned (along with reasons) in the SFCR In the SFCR, you may refer to or make use of equivalent information available elsewhere in the public domain (although CEIOPS do not consider it appropriate to refer through hyperlinks to other documents - rather reference if further information is provided elsewhere)

Page 14

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Implementation procedures



Solvency II introduction & recap



Implementation procedures



Experiences & lessons from QIS 5



Looking ahead

Page 15

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Some key questions regarding your Solvency II implementation 2009 May 2009 – Framework Directive Approved

Implementation activity

2011

2010 QIS5

QIS5 feedback

Planning for implementation in 30 countries and associated territories

IMAP dry run (June 2010 to October 2011)

Vision & Gap analysis

Road Map design

Detailed Implementation plan and activities

2012

Internal Model Implementation – Application 31 December 2012 Process (IMAP) submission Transposition into domestic law and regulation

IMAP by April 2012

Full implementation

Build and test Embed Implementation

► What level of detail does your implementation plan go to? (e.g., high-level road map and detail activity plan) ► Does your plan build on the output from the gap analysis and identified solutions to mitigate all deficiencies? ► Has your plan been reviewed and approved by the governance committee, with agreed budget, headcounts, and timeline that are realistic? ► What do you plan to do next with your plan? Page 16

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Illustrative SII governance and program structure – ’making it happen’ A well defined SII governance/program structure will ensure rapid decision-making, and effective execution of the SII implementation plan Program Governance

Key Features ►



Horizontal & vertical workstreams to drive aligned business requirements and a complete business case

Steering Committee

Technical Review Panel

Program Directorate

Design Authority Team

Dedicated technical challenge and support at all levels of the program

Program Management

Program Management Office

Workstreams Internal Model

Risk & ORSA

Reporting & Disclosures

Optimisation

Technology/Data and Tools Enabling Workstreams



Process & Controls Change Management Documentation

Page 17

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Product Pricing and Development

Resourcing for SII and understanding its implications on existing headcount 30

SII headcount means a x% growth

25 6

5

20 4 15

2 3 1

3

10 15 5

16 12

10

1 3 4

0 Analyst

Senior Analyst Current team

Assistant Manager

Manager

Open positions

Senior Manager SII resources required

Considerations on resourcing: ►

Where to hire resources from?



Internal vs. external use of resources and its cost implications?



Impact on existing headcount and integrating new resources into business as usually activities?



Speed at which resources can be obtained? Impact on SII programme?



When do the resources need to be brought it? All at a point in time? Spread over time?

Page 18

Appointed Actuary Symposium: Actuarial Society of Hong Kong

2 Director

Example of Detailed Road Map – Risk Modelling & Reporting Phase 1 Understand & Design SII Reporting Metrics & Modeling Requirements

2H 2009

SII Reporting Methodology

Overall SII Reporting Framework ALM Model

1H 2010

1

2H 2010

4 5

QIS5 Solo delivery by Oct 2010

6 7

Phase 2 – SII Reporting Implementation and Testing Phase 3 Transition from Development to Production Page 19

Implementation of the internal model

8

ESG

Internal Finalisation of Models & External Model Audit

Business As Usual

3

ALM Modeling

Validation, documentation & User Testing

2H 2012

2

Asset Valuation Implementation

Financial Reporting Infrastructures

1H 2012

Define and document required enhancement to models to meet requirements

Economic Scenario Generator (ESG) Complete QIS5

2H 2011

1H 2011

9

Complete design and implement of valuation processes and reporting

10 11

External Audit Process being Carried Out

12

SII Reporting Full Testing & Dry Runs SII Reporting System Go Live

Parallel runs of Q1 ~ Q3 2012

13

Appointed Actuary Symposium: Actuarial Society of Hong Kong

System launched

Example of Detailed Road Map – Risk Management

Review of Governance

Review of Risk Appetite & Tolerance Limits

2H 2009

1H 2010

2

Set Risk Tolerances per Major Risk Category

3

Define Management Response to Risk Identification and Appetite Define Control Activities to Address Risk Management requirements

Build Process Catalogue

Embed Risk Management Changes

Review of ORSA

Define and Design Process

6 7

Embedding Change Management Programs Completed

8

Design of ORSA Process Completed

Final Documentation of Operational Risks Completed

Assessment of other Risk categories

10

Use Test

Definition of Control Activities Completed

5

9

Define Independent Review of ORSA

2H 2012

Definition of Management Response to Risk Management Completed

4

Identify and Assess Operational Risks

Build ORSA Report Formats

1H 2012

2H 2011

Definition of Risk Appetite Completed Allocation of Risk Tolerances per Major Risk Category Completed

1

Define and Determine Risk Appetite

Assess / Update Governance Manuals, Terms of Reference and Role Definitions

Page 20

1H 2011

2H 2010

Final Documentation of Other Risk Categories Completed

11 12

Definition of Independent Review of ORSA Completed

13

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Use Test Complete

Business As Usual

Annually review and update as required

The biggest issue/difficulty faced by company in its Solvency II implementation ►

Resource, resource, resource !!!



Understand the scale and complexity of the SII project and reflecting it realistically in the time, resource and cost estimate



Deciding the appropriate detail action plans for both short term and medium to long term activities, including the key workstream leaders and SII program structure



Allowing flexibility to cope with surprises arising from the Level 2 Implementing Measures and Level 3 Guidance



Allowing for hand-offs and dependencies between workstreams and different department



Other

Page 21

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Experiences & lessons from QIS 5



Solvency II introduction & recap



Implementation procedures



Experiences & lessons from QIS 5



Looking ahead

Page 22

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Experiences & lessons from QIS 5 QIS 5 Overview Overview ►

The final QIS5 Technical Specification was issued on 6 July 2010 after discussions on the Draft Specification with selected stakeholders (CEA, AMICE, CRO Forum, CFO Forum, ECIROA, FERMA and Groupe Consultatif).



The Commission has emphasized the importance of dealing with all areas of the exercise comprehensively, and is expecting high quality submissions from firms on which to base its decisions.



A number of key changes from the draft technical spec: ►

Changes in calibrations – generally less favourable compared to QIS4, but more favourable compared to CEIOPS Consultation Papers / Final Advice.



Changes in methodology – additional sub-modules proposed and refinements in methodology for existing (sub)modules compared to QIS4.



The technical specifications should not be seen as the final outcome as the intention is to publish the Level 2 implementing measures once the results of QIS5 are known.



Results not required to be submitted to OCI.

QIS5 objectives ►

To provide detailed information on the quantitative impact of future Level 2 implementing measures .



To encourage industry preparation and to: ►



Identify areas where internal processes, procedures and infrastructure may need to be enhanced and encourage improvements to data collection processes

To provide a starting point for an ongoing dialogue in preparation for the new supervisory system.

Page 23

Appointed Actuary Symposium: Actuarial Society of Hong Kong

QIS5 provides an ideal checkpoint for Solvency II programmes to: ►

Educate stakeholders with quantitative evidence of the potential impacts, informing lobbying activity.



Review and realign Solvency II plans based on your experience of performing QIS5.



Extending the dialogue between local operating companies and European parent.

Experiences & lessons from QIS 5 Issues & Challenges - Overview Key issues and challenges encountered while carrying out QIS 5 exercise: ►

Application of contract boundary condition.



Calculation of expected profits in future premiums (“EPIFP”).



Calculation of risk margin.



Severity of standard formula currency risk stress.



System and resource limitations.

Page 24

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Experiences & lessons from QIS 5

Issues & Challenges – Contract Boundary



Definition of contract boundary as per QIS 5 Technical Specifications: ►

where an undertaking has the unilateral right to terminate the contract; or



where an undertaking has the unilateral right to reject premiums; or



where an undertaking has the unilateral right to amend premiums or benefits,

at some point in the future, then any cash flows pertaining to time period after that date should not be included in the liability calculations. ►

For insurers in the region, yearly renewable business likely to be affected.



Likely to affect the BEL negatively as these business tend to have a negative BEL value.



Current debate on application of contract boundary unit-linked contracts.



Companies might calculate (submit) two set of results (one follow QIS 5 guidance exactly, and one follow their interpretation) given the definition of contract boundary is unclear

Page 25

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Experiences & lessons from QIS 5

Issues & Challenges – EPIFP Calculation ►

QIS 5 introduces the concept of expected profits in future premiums (“EPIFP”).



Explicit recognition of expected profits built into future cash flows on best estimate basis.



EPIFP value is to be included as Tier 1 capital for Own Funds calculations.



Methodology for calculating EPIFP: ►

Calculate technical provisions (ex-risk margin) using best estimate assumptions. [A]



Calculate technical provisions (ex-risk margin) assuming no future premiums are received. [B]



Technical provision (ex-risk margin) from [B] less that from [A] is the EPIFP value (if negative, EPIFP set to zero).



In calculating [B], benefit levels are adjusted to be consistent with assumption of no future premiums. This adjustment not trivial as use of retrospectively or prospectively calculated surrender benefits will include elements of past or future profits.



Severity of issue depend on reliance on EPIFP to meet the required capital requirements.

Page 26

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Experiences & lessons from QIS 5

Issues & Challenges – Risk Margin Calculation ►

Recall - risk margin calculation is a cost of capital approach, where the capital is the projected SCR. Projected SCR to include: ►

unavoidable market risk;



life underwriting risk;



counterparty default risk relating to reinsurance and SPV reinsurance arrangements; and



operational risk.



Projection of the SCR requires nested stochastic calculations – stresses to be applied for each future time period.



Possible modeling solutions being explored include replicating portfolios and formula fitting techniques.



Meanwhile, QIS 5 technical specifications set out a number of simplifications. Hierarchy of simplifications: ►

full calculation of projected required SCR (no simplification used);



approximate only certain risks in some of the required SCR;



approximate whole SCR for each future year;



approximate all future required SCR “at once”;



approximate risk margin as a percentage of the best estimate liabilities.



In deciding simplification to be used, need to consider the information, resources and modeling capability available.



May impact the capital position of the firm as risk margin could be a material value.

Page 27

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Experiences & lessons from QIS 5

Issues & Challenges – Currency Risk Stress



Standard formula stress for currency stress is an increase and decrease of 25% in net foreign currency exposure.



This calibration may not be suitable for the Hong Kong dollar /United States dollar relationship given the close relationship of the two currencies in recent history.



Some participants are viewing this as being too penal.



Likely to have a significant impact on the SCR calculations.

Page 28

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Experiences & lessons from QIS 5

Issues & Challenges – System and Resource



System limitations: ►

Data systems not able to support the extraction of data at the expected level of granularity required for Solvency II Pillar 1 compliance. ►



Modeling capabilities not sufficiently refined to model key liability and asset portfolio features. ►



Example – historical and forecast premium information by line of business.

Example – dynamic policyholder behavior and equivalent scenario.

Resource limitations: ►

Lack of buy-in from management due to submission to OCI not required. ►



Lack of personnel with the relevant knowledge/experience. ►

Page 29

Possible solutions: educate stakeholders; build relevant Solvency II features into business as usual activities.

Possible solutions: tap knowledge of colleagues in European HQ; start recruiting and training now; engage consultants for specific modules.

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Looking ahead



Solvency II introduction & recap



Implementation procedures



Experiences & lessons from QIS 5



Looking ahead

Page 30

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Looking ahead Expected Implementation Challenges as SII Progress Use test

Significant business changes

► This will be one of the most challenging areas of the new regime ► The impact will be far reaching and as a result the implementation challenges will be significant

► In the end state of Solvency II, there will be significant changes to the models, management information, data, infrastructure and procedures ► There are commercial and profitability implications arising out of implementation

Implementation challenges Links to other projects

Cultural changes

► Solvency II can potentially link directly or impact on projects already ongoing.

► Changes in the culture would be required to reflect new metrics and processes

► Ensuring that work done in these workstreams is leveraged appropriately to ensure no duplication of effort will be a key role of the Solvency II Steering Group.

► There is a necessity to manage the business to different metrics consistently across the group…

Page 31

► …and to reward people on the basis of these new metrics.

Appointed Actuary Symposium: Actuarial Society of Hong Kong

Looking ahead Impact from IFRS 4 Phase II

Page 32

3 September 2009

Training Materials

Thank You Appointed Actuary Symposium 3 November 2010